商务中心施工组织设计中英文摘要范文

资料分类:土木工程设计资料 - 论文摘要范文参考资料 | 发布形式:资料共享 | 更新时间:2017-09-04 显示全部楼层

  摘  要
  本设计名称为盐城新城商务中心施工组织设计,位于盐城市,结构类型主体选用异形柱框架结构,地下三层、地上十层局部十一层,建筑面积10440.1㎡,建筑高度35.060米,抗震设防烈度6级,设计使用年限50年,地上部分耐火等级二级,屋面防水等级II级;D4地下室部分分为人防区与非人防区,抗震设防烈度6级,建筑耐火等级一级,种植屋面防水等级一级,地下室防水等级二级。本工程所注±0.00标高相当于绝对标高3.900米)。
  本施工组织设计严格按照招标文件的规定和设计图纸、房屋建筑施工规范的要求;保证重点、统筹兼顾;根据施工现场的地质、地貌、气候等实际情况,结合施工力量和管理模式,本着以机械为主,人工施工为辅的方法,科学组织,充分发挥优势,达一流品质,创优质工程的原则编制。根据招标文件精神,就本工程项目编制施工组织设计,由以下施工内容组成:施工组织编制说明、工程概况、施工组织机构及人员配置、施工方案和技术措施、质量管理体系与措施、施工现场平面布置、进度计划及保证措施、劳动力安排计划、施工机具配备、材料供应计划、安全生产、文明施工、减少环境污染、环保体系与措施等。
  关键词:施工方案 施工进度计划 总平面布置
  yanchengconstruction organization design
  ABSTRACT
  This design name for north of yanchengstar river district no. engineering construction design, located in Wuxi City, the main structure type selection of special-shaped column frame structure, 20# underground in three layers, the ten layer local 11 layer, building area of 10440.1 square meters, building height 35.060 meters, seismic fortification intensity 6 class, use fixed number of year for 50 years. On refractory grade two, roof waterproof grade II; D4 underground chamber parts for civil air defense zone and non defense area, seismic fortification intensity level 6, building fireproof rank level, planting roofing waterproofing rank level, basement waterproof grade second class. This project note + 0 is equivalent to the absolute elevation elevation of 3.900 meters
  The construction organization design strictly in accordance with the provisions of the tender documents and design drawings, housing construction standard construction requirements; ensure focus, overall consideration; climate, supplemented by artificial construction method, scientific organizations, give full play to its advantages, According to the spirit of the bidding documents, on the engineering project preparation of construction organization design, by construction, the following composition, the construction organization, the general situation of the projec, construction organization and personnel allocation, the construction scheme and technical measures, quality management system and measures for implementation, construction site layout, schedule and guarantee measures, labor plan construction machinery equipment, material supply plan, safety in production, civilized construction, reduce environmental pollution, environmental protection system and measures.
  Key words: construction project; construction schedule; general layout