根据毕业设计的要求,结合本工程的具体情况和有关现行规范、规程等资料,编制的单位工程施工组织设计文件。
本设计名为铁岭城市花园住宅楼施工组织设计与施工图预算,位于铁岭市。建筑结构形式为框架剪力墙结构,总建筑面积:5684.67m2,共有11层,总高34.165m。抗震等级3级,设计使用年限50年。
本住宅楼施工组织设计主要包括:编制依据、工程概况、施工组织机构及职责、施工部署、施工进度计划、施工准备与资源配置计划、主要施工方案、施工现场平面布置、工程质量保证措施、施工“安全、文明、卫生”管理措施、施工项目季节性施工措施。其中针对各个分部分项工程的特点、施工难易程度、工期和质量要求,编制出切实可行的施工方案,同时绘制出所需要的图纸,对整个工程施工组织设计进行详细的编写,并绘制进度图。
为了完成本工程对施工项目管理规划的编制,根据工程的实际情况,制定工程的整个施工方案、技术措施、质量目标及保证措施,质量控制点的设置及预控措施。采用了施工总平面图、横道图、网络图,结合相关资料,更加清晰地确定了施工方案和施工部署,并且明确了进度施工计划,同时明确了工程的质量管理、安全管理等内容。从技术上、经济上反复进行对比、分析,选择出一个最佳施工方案。使之不仅技术上可行,而且经济上合理,达到加快进度,降低成本,减少浪费的目的。在施工阶段,还可以从施工的角度向建设单位或设计单位提出一些合理化建议,以降低消耗,节约费用,施工安全可靠。制定环保措施,控制噪音尘埃污染,减少投诉;制定安全生产措施,建立安全保证体系,最终完成该楼的建设工作。
关键词:住宅楼;施工组织;施工方案;施工部署
According to the requirements of graduation design, combined with the specific circumstances of this project and information about the current rules and regulations and so on, by the unit project construction organization design documents.
This design named tieling city garden residential building construction organization design and construction drawing budget, is located in tieling city.Building structure form is frame shear wall structure, a total construction area: 5684.67 m2, with a total of 11 layers, total 34.165 m high.Seismic grade level 3, the design use fixed number of year for 50 years.
This residential building construction organization design mainly includes: compilation basis, project general situation, construction organization and responsibility, construction deployment, construction schedule, construction preparation and resource allocation plan, main construction scheme, construction site layout, engineering quality assurance measures, the construction of \"safety, health, civilization\" management measures, seasonal construction project construction measures.Among them according to the characteristics of each division subdivisional work, degree of difficulty of construction, the construction period and quality requirements, develop the feasible construction scheme, and mapped the required drawings, written in detail of the whole project construction organization design, and map the progress.
In order to complete the project on the planning of construction project management, according to the actual situation of the project, make project of the construction plan, technical measures, quality goals and guarantee measures, quality control points of setting and control counter measures. Adopted the construction plan, crossing chart, network diagram, combined with the related data, more clearly identified the construction scheme and construction deployment, and clear the progress of the construction plan, at the same time the quality of engineering management, security management, etc. Repeatedly from the technical and economic comparison and analysis, choose the one best construction scheme. Make it not only technically feasible and economically reasonable, to speed up the process, cost reduction,the purpose of reducing waste. In construction stage, also can from the Angle of construction put forward some reasonable Suggestions to the construction unit or design units, to reduce consumption, save cost, construction safety and reliability. To develop environmental protection measures, control the dust pollution, noise reduction complaints; Develop production safety measures, establish safety assurance system, finally complete the office building construction work.
Keywords: residential building;construction organization;construction plan;con-struction deployment. |